183 BESS Delivered from China to Bulgaria in 30 Days
Chartered vessel from China to Bulgaria | DG cargo (UN 3536) | Full inland execution.


Planning a BESS project? Choose the right logistics model from day one.
Energy Infrastructure. Executed for Over Three Decades.
For more than 30 years, Unimasters has been delivering complex energy and project cargo across Bulgaria and the region.
Battery Energy Storage Systems are not a new segment for us. They are the next chapter in an energy transition we have supported for decades.
See one of our latest projects in action
Discover how Unimasters successfully transported BESS cargo from China to Bulgaria, ensuring full compliance, safety and multimodal coordination.
Case Study: 183 BESS Units. China to Bulgaria. 30 Days.
When time, regulatory compliance, and cargo sensitivity intersect, logistics becomes a strategic decision. Here is how we executed the project.
The Challenge
183 Battery Energy Storage Systems
Heavy containers (35–45 tons)
DG cargo classification
Strict deadline
Limited carrier acceptance
Risk of storage penalties
Commissioning timeline was critical.
The Solution
Chartered a dedicated vessel
Routed via Suez
Coordinated origin & DG documentation
Managed port handling in Varna
Executed inland ADR transport to final site
Risk of storage penalties
Result: Delivered on time. No storage costs. Full operational control.
Which BESS Scenario Are You In?
Every BESS project is different. Your logistics strategy should be too.
Charter Vessel Strategy
Full capacity control. Fastest routing. Best for commissioning-critical projects.


Why BESS logistics is different?
Battery energy cargo is not standard freight. It requires:
UN 3480 / 3481 / 3536 compliance
DG + project cargo integration
Carrier-specific approvals
State-of-charge documentation
Strict commissioning alignment
What Unimasters Controls?
We control the full logistics chain - from factory gate in Asia to energy park in Bulgaria.
Carrier & DG pre-approval before booking
Routing optimisation for Bulgaria & region
Port handling & customs execution
Heavy / ADR inland transport
Single accountable partner


Not sure which model fits your project?
Request a preliminary routing and budget assessment.
Get Expert ReviewWhy Engage Early?
Early logistics involvement ensures:
Accurate logistics CAPEX budgeting
Faster permitting
Reduced delay risk
Optimised routing during project design
Knowledge Hub
Learn more about the key stages, risks, and best practices involved in transporting BESS systems.
Planning a BESS project in Bulgaria or Europe?
Let’s define the right logistics strategy before shipment planning begins.
Project Cargo | DG Logistics | Multimodal | Customs
Unimasters - your logistics partner for battery energy infrastructure.